Local Development Scheme - Local plan timetable

The key stages for this timetable are set out below with an overview of each stage.

View our Bassetlaw District Council Local Development Scheme Timetable

 
Local Plan Development Stage Timetable

Evidence Base Work

November 2015 to May 2020

Initial Draft consultation

Completed October to December 2016

Draft Plan consultation Part 1: Strategic Plan

November 2018 to December 2018

Draft Plan consultation Part 2: Local Plan

June 2019 to July 2019

Publication Draft consultation

January 2020 to February 2020

Submission of the Local Plan

June 2020

Public Examination

November 2020 to December  2020

Formal adoption

February 2021

Total plan preparation

September 2015 to February 2021

 

 

 


Last Updated on Tuesday, April 30, 2019

The key stages for this timetable are set out below with an overview of each stage.

View our Bassetlaw District Council Local Development Scheme Timetable

 
Local Plan Development Stage Timetable

Evidence Base Work

November 2015 to May 2020

Initial Draft consultation

Completed October to December 2016

Draft Plan consultation Part 1: Strategic Plan

November 2018 to December 2018

Draft Plan consultation Part 2: Local Plan

June 2019 to July 2019

Publication Draft consultation

January 2020 to February 2020

Submission of the Local Plan

June 2020

Public Examination

November 2020 to December  2020

Formal adoption

February 2021

Total plan preparation

September 2015 to February 2021

 