Mattersey Parish Council formally submitted the final version of their neighbourhood plan, and supporting documents, to Bassetlaw District Council for independent examination on the 10 August 2018. Public consultation (regulation 16) was undertaken for 6 weeks, closing on the 21 September 2018. 

The independent examination of the plan was conducted during late 2019 into early 2019, with the final Examiner's Report issued on the 15 March 2019 (included below). The Examiner's Report was approved by Bassetlaw District Council at a meeting of Full Council on 27th June. The recommended modifications are currently being made, with the local referendum due to be held on Thursday 5th September 2019. 

Stage Date
Neighbourhood Area Designated 18 April 2015 
Draft Plan Published 17 March 2018 
Final Plan Submitted 10 August 2018 
Examiner's Report Published 15 March 2019
Referendum  5 September 2019

 

Website: https://mandmtneighbourhoodplan.weebly.com/neighbourhood-plan.html

Supporting documents

Some documents within our Neighbourhood Plan pages are produced externally. These may not be suitable for users of assistive technology. Request an accessible format.

Submission stage

Examination

Referendum stage

Please see the dedicated Mattersey Neighbourhood Plan Referendum webpage for all documentation, including the Neighbourhood Plan (Final Version)

 

 


Last Updated on Friday, August 02, 2019

 

Mattersey Parish Council formally submitted the final version of their neighbourhood plan, and supporting documents, to Bassetlaw District Council for independent examination on the 10 August 2018. Public consultation (regulation 16) was undertaken for 6 weeks, closing on the 21 September 2018. 

The independent examination of the plan was conducted during late 2019 into early 2019, with the final Examiner's Report issued on the 15 March 2019 (included below). The Examiner's Report was approved by Bassetlaw District Council at a meeting of Full Council on 27th June. The recommended modifications are currently being made, with the local referendum due to be held on Thursday 5th September 2019. 

Stage Date
Neighbourhood Area Designated 18 April 2015 
Draft Plan Published 17 March 2018 
Final Plan Submitted 10 August 2018 
Examiner's Report Published 15 March 2019
Referendum  5 September 2019

 

Website: https://mandmtneighbourhoodplan.weebly.com/neighbourhood-plan.html

Supporting documents

Some documents within our Neighbourhood Plan pages are produced externally. These may not be suitable for users of assistive technology. Request an accessible format.

Submission stage

Examination

Referendum stage

Please see the dedicated Mattersey Neighbourhood Plan Referendum webpage for all documentation, including the Neighbourhood Plan (Final Version)


Last Updated on Friday, August 02, 2019