Building Work Inspections

Listed below are the various stages (where applicable) when Building Control should be contacted to arrange an inspection of work.

 

The Building Regulations specify certain statutory notifications where notice must be given.  Failure to notify may result in work having to be exposed for inspection.

 

Booking an inspection:

 

Please do not use the online booking system for visits required for the current day.  If you require a “same-day” visit, please telephone Planning Services before 10.00 a.m. 

 

In calculating the period of days, ‘days’ means any period of 24 hours commencing at midnight and excludes any Saturday, Sunday or Bank Holiday.

 

Notice of commencement should be given two days before any work is undertaken.

Please note that we cannot guarantee specific times for inspections.  It is our usual practice to visit between 11.00 am and 3.30 p.m.  Where the number of inspections is excessive we will consider carrying the inspection to another day.

 

 

Item Stage

Statutory

Notification

Period of

Notice Required

1 Commencement Yes 2 Days
2 Excavations for foundations Yes 1 Day
3 Foundations (concrete laid) No 1 Day
4 Oversite (before covering) Yes 1 Day
5 Damp Proof membrane (prior to insulation/concreting) Yes 1 Day
6 Oversite (concrete laid) No 1 Day
7 Damp Proof Course to walls Yes 1 Day
8 Floor Timbers No 1 Day
9 Steelwork/Lintels (including padstones and bearings) No 1 Day
10 Roof Timbers No 1 Day
11 Electrical First Fix No 1 Day
12 Insulation (specify location) No 1 Day
13 Drains Laid (before covering up) Yes 1 Day
14 Drains Test (after backfilling and covering up) Yes 5 Days
15 Occupation of the Building Yes 5 Days
16 COMPLETION (of all work) Yes 5 Days
17 Other inspection request (please specify) No 1 Day

 

Additional inspections may be required depending on the type of project, in order to view items of work that will subsequently be covered up.  These may include inspection of roofs, lintels and structural supports, insulation, electrical installations, fire stops and fire protection.

Applicants must advise Building Control at the time of depositing an application whether the electrical installation is being carried out by a person registered under a Competent Person scheme.

 
Last Updated - 13/06/2012