Permit applications for all new or
substantially changed installations are received by the Local
Authority, who have 10 working days to establish whether the
applicant has included sufficient information to determine the
application duly made.
Application form and fee
The application must be accompanied by the appropriate
application fee, which varies depending on the complexity of the
process. Current fees are available on the
Defra website.
The following application forms are provided for Part A2 and
Part B processes. However, operators are strongly
encouraged to enter into pre-application discussions
before making their formal application.
To discuss an enquiry or application please contact us on 01777
713764 or complete our online enquiry form.
Consultation process
The duly made application is placed on
the Council’s public register and becomes the subject of a 28 days
statutory consultation exercise.
A copy notice of the application is
normally placed in a local newspaper, and all reasonable objections
are given due considered during the determination period.
Following the consultation period the
application is determined by the Local Authority officer and a
permit to operate is issued.
Last Updated - 12/03/2013